SCHEDULE

PROJECT KICK-OFF MEETING WITH STUDY TEAM MAY 15, 2007
DATA GATHERING MAY–AUGUST, 2007
PUBLIC INPUT MEETING TO REVIEW EXISTING CONDITIONS SEPTEMBER 26, 2007
DEVELOP RECOMMENDATION PLANS FOR STUDY TEAM REVIEW AUGUST, 2007–MARCH, 2008
SHARE PRELIMINARY RECOMMENDATIONS APRIL 23, 2008
REFINE FINAL PLAN RECOMMENDATIONS APRIL–JUNE, 2008

This schedule concludes with review of final recommendations in May 2008. This process does not include any design, Right-of-Way acquisition, utility relocation or actual construction, which would need to proceed following the completion of this study.

Dates are tentative and subject to change.